View as PDF ASME Engineering took on the Watford Data Centre project to provide internal structural steel work for offices and staircases within the 5 acres site, in addition to the existing building.

Working to a tight deadline, with 400 other people also on site at the same time, health and safety was paramount and therefore it was vital regular health and safety review meetings took place with the main contractor.

With the requirements for data centres being very specific, ASME Engineering had to ensure all steel was galvanised. We took along our own office and supplied our own cranes. In total 1000 tonnes of external gantry steelwork was installed on this project

Contract value:
£3,500,000
Location:
Watford
Duration:
16 Months